Penneshaw Desalination Plant

A small seawater desalination plant was constructed at Penneshaw on Kangaroo Island in 1999.

Seawater is drawn into the plant through an intake pipe and pre-screened. UV disinfection is used to minimise biological growth and filters remove most particulate matter. The filtered seawater is forced under high pressure through reverse osmosis membranes that allow fresh water to pass through, with very little salt. The desalinated water is re-mineralised with carbon dioxide (CO2) and marble chips before it is disinfected with chlorine and supplied to customers.

The plant can produce 400 kL of drinking water per day.

*1 kilolitre = 1000 litres

Penneshaw desalination plant

Hawker Desalination Plant

Water for the Hawker township comes from a local groundwater basin.

The groundwater is very hard and it is high in total dissolved solids, which makes the water very salty. While this water meets the Australian Drinking Water Guidelines (2011) health criteria it tastes salty.

Working together with the Flinders Ranges Council we found a solution that would work in a remote location and now we improve the taste of the water at the Hawker Desalination Plant.

The plant began operating in August 2014 and can produce 500 kL of drinking water per day.

Hawker desalination plant

Leigh Creek Desalination Plant

The management of water services in Leigh Creek shifted from Flinders Power to us, in December 2016.

Leigh Creek draws drinking water from a number of local bores and due to the relatively high salinity of the ground water supply, a small desalination plant is used to treat the water.

The plant can produce up to1.25 ML of drinking water a day.

APY Lands and Yalata Desalination Plants

Being able to successfully operate desalination plants is especially useful in remote locations such as the Anangu Pitjantjatjara Yankunytjatjara (APY) Lands, to help ensure reliability and sustainability of the drinking water supply for everyone living in these communities.

We operate desalination plants at Indulkana, Mimili, Kaltjiti (Fregon) and Yunyarinyi (Kenmore Park) in the far north of South Australia, and Yalata on the west coast.

These plants treat water from local bores to ensure it meets the Australian Drinking Water Guidelines (2011).

Yalata

- Current plant was commissioned in 2006
- We installed a 40 kW solar system with battery storage in 2016
- Total capacity of 160 kL/day

Indulkana

- Commissioned in 2014.
- 14 kW solar installed September 2018, with plant timed to run during daylight hours only
- Total capacity of 40 kL/day

Indulkana Desalination Plant

Mimili

- Commissioned in 2013
- Total capacity of 60 kL/day

Kaltjiti (Fregon)

- Commissioned in 2005
- Total capacity of 160kL/day

Yunyarinyi (Kenmore Park)

- Commissioned in 2018
- 10 kW solar with battery storage installed in 2016
- Total capacity of 20 kL/day

Murputja

- Commissioned in July 2019
- 24 kW solar with battery storage installed in 2019
- Total capacity of 60 kL/day

Murputja Desalination Plant

Proposed desalination for the Eyre Peninsula

We are committed to providing our customers with safe, clean drinking water.

A dependable supply requires a reliable source. The majority of water on the Eyre Peninsula is sourced from groundwater which is drawn from the Uley South Basin with about 20 per cent coming from the River Murray via the Morgan to Whyalla pipeline.

Together with the Department for Environment and Water we are measuring and monitoring critical indicators that assess the health of groundwater resources including the Uley South Basin.

Mindful of protecting the groundwater resources following three consecutive years of low rainfall and recharge of the Uley South Basin, we are now progressing the option to supplement the Eyre Peninsula’s water supply with seawater desalination.

Our focus is on managing the health of water catchments so we can deliver safe, clean drinking water to our customers living and working on the Eyre Peninsula while protecting and enhancing the area for future generations.

Read more about long term planning and proposed desalination for the Eyre Peninsula

  • Major faults

  • Underway

  • Anzac Hwy
  • Glenelg East
  • 15/12/2019
  • Water Supply On
  • 15/12/2019 02:01 PM - We are attending to an incident in Glenelg East with no interruption to the water supply. The safety of our crews and customers comes first, and we always aim to minimise inconvenience by restoring services as quickly as we can. Reference Number WO: 07254795.
  • See all major faults

  • Scheduled works

  • Underway
  • Sprod Av
  • Toorak Gardens
  • 15/12/2019
  • Temporary Supply Interruption
  • Estimated start time and water supply off: 17/12/2019 09:00 AM
    Estimated restore time and water supply back on: 17/12/2019 06:00 PM

    We’re improving your services and undertaking maintenance work in Toorak Gardens. Sometimes our crews need to temporarily interrupt the water supply to our customers and/or manage traffic while they are working. Temporary traffic management may remain in place until reinstatement of the impacted road is complete. We always aim to minimise inconvenience by restoring services as safely and quickly as we can.


  • See all scheduled works