Jetty Road Glenelg Water Main Renewal

Jetty Road Glenelg Water Main Renewal

We have completed the installation of a total 970 metres of new water main at Glenelg – including under the southern side of Jetty Road – along with all other associated works.

Work began in late 2017, was put on hold to allow for the summer trade and peak tourist period, and then resumed in July 2018. The bulk of the project was completed in late August, with remaining minor works such as road reinstatement and line-marking, decommissioning parts of the old water network and site clean-up carried out in the past few weeks.

Of the 970 metres of new water main installed in the area, around 370 metres was renewed under Jetty Road, with the remainder moved to parts of Newmans Lane, Cowper Street and Milton Street.

We would like to thank the local community, who we partnered with to ensure business as usual could continue throughout the works, especially the City of Holdfast Bay and Jetty Road Mainstreet Committee.


Existing water main
Water main installation complete
Water main installation remaining

Further information

Call: 1800 812 362
Email: project@sawater.com.au

  • Major faults

  • Underway

  • Balaklava Rd
  • Auburn
  • 22/10/2018
  • Water Supply On
  • 22/10/2018 06:45 PM - We are attending to an incident in Auburn with no interruption to the water supply. The safety of our crews and customers comes first, and we always aim to minimise inconvenience by restoring services as quickly as we can. Reference Number WO: 06610492.
  • See all major faults

  • Scheduled works

  • Underway
  • Frome St
  • Adelaide
  • 22/10/2018
  • Temporary Supply Interruption
  • Estimated start time and water supply off: 23/10/2018 09:00 PM
    Estimated restore time and water supply back on: 23/10/2018 06:00 AM

    We’re improving your services and undertaking maintenance work in Adelaide. Sometimes our crews need to temporarily interrupt the water supply to our customers and/or manage traffic while they are working. Temporary traffic management may remain in place until reinstatement of the impacted road is complete. We always aim to minimise inconvenience by restoring services as safely and quickly as we can.


  • See all scheduled works