Western Adelaide Wastewater Network Upgrade

Western Adelaide Wastewater Network Upgrade

What is the project?

We have now completed the installation of 2.5km of new sewerage main, mostly through the Adelaide Park Lands. The new pipeline runs from West Terrace to an existing main at the North Adelaide Golf Course. 

Why is it important?

The sewerage main upgrade will accommodate for future population growth in the Adelaide CBD and Adelaide's residential south-eastern suburbs.

What can I expect?

All construction works are complete and the upgraded sewerage main is now operational.

During September and October 2017, we will be undertaking reinstatement works in the Adelaide Park Lands. We are working closely with the City of Adelaide and other key stakeholders to coordinate the installation of turf, hydro seeding and reinstatement of pathways.

Where can I go for more information?

If you have any questions regarding the project, please contact the Stakeholder Engagement Team on 7424 2806 or email project@sawater.com.au.

  • Major faults

  • Reported

  • California St
  • Nailsworth
  • 25/11/2017
  • Water Off
  • Last Updated: 25/11/2017 09:32 AM - We are on-site responding to an incident in Nailsworth. Water may not be available in the surrounding area until 25/11/2017 04:00 PM. Traffic restrictions may also apply. Reference Number WO: 06114942.
  • See all major faults

  • Scheduled works

  • Underway
  • Anzac Hwy
  • Plympton
  • 25/11/2017
  • Supply Interruption
  • Estimated start time (water off): 29/11/2017 09:00 AM
    Estimated restore time (water back on): 29/11/2017 04:00 PM

    We’re committed to improving your services and are undertaking maintenance work in Plympton. Water supply in the surrounding area may be impacted during the above times. Traffic restrictions may also apply.


  • See all scheduled works