SA Water’s suite of upgrades to augment the water network across the Murraylands has achieved a major milestone this week, with more than half of the 7,000 metres of new water main now in the ground.

During the past two months, crews have been working through sections of Monarto Safari Park to lay new pipes to duplicate four existing water mains – increasing the capacity of the region’s water supply network.

Reaching this milestone has culminated in the rare task of installing a section of one of the pipes underneath the Melbourne to Adelaide rail corridor, with specialised drilling equipment required to bore beneath the track.

SA Water’s Senior Manager of Capital Delivery Peter Seltsikas said a different pipe material will be used under the railway track to help preserve the structural integrity of the main, and protect surrounding infrastructure.

“To reach this stage of the upgrade, we’ve been working closely with the Australian Rail Track Corporation to safely facilitate crews using heavy machinery either side of the corridor as they install the new pipe,” Peter said.

“Our crews have been operating a horizontal directional drill to bore a 60-metre-long tunnel under the track for the pipe to be pulled through via a trench on the other side at the fringes of Monarto Safari Park, where they’re currently wrapping up the final section within the park.

“Rather than lay PVC pipes like we’re using elsewhere for the project, we’re using high-density poly pipes, due to their increased flexibility to withstand ground movement and their ability to be welded together and pulled through the tunnel.

“This is particularly beneficial given the greater potential impact a leak on this section of pipe may have, given the importance of the rail infrastructure. To provide more protection, we will encase it in a slightly larger pipe to help prevent any damage to the track in the event of a leak.

“Based on the land’s topography, the pipe will sit at a maximum depth of five metres below the raised track before it connects into PVC pipes, as the alignment travels south and reaches Old Princes Highway.

“Crews have taken advantage of the drier winter conditions and made wonderful progress over the past eight weeks, even making a few friends with Monarto Safari Park’s giraffes who love to have a stickybeak from their paddock and have taken it upon themselves to become extra site supervisors!”

The project also includes an upgrade to SA Water’s pump station in nearby White Hill to support the increased flow of water, along with construction of a new booster pump station at Monarto.

“Designs for this work are well underway, with construction expected to commence in early 2024 once we’ve completed laying our new pipes,” Peter said.

Contact:

Phone:

Email:

Contact

For media enquiries, please call or email SA Water’s media team:

Phone: (08) 7424 2477
Mobile: 0477 300 197 (24/7)
Email: media@sawater.com.au

For all other SA Water-related enquiries, please call our Customer Care Centre on 1300 SA WATER (1300 729 283).

Search the media centre

By keyword:

By date range:

From calendar icon
To calendar icon
-->